Padel Court Construction

Guide · Clubs and landowners · 3 min read · Updated 17 November 2026

How a Padel Court Is Built: Stages and Timeline

Short answer

Building a padel court runs through feasibility, planning, groundworks and base, then court installation, turf and lighting. Planning decisions on many applications take around eight weeks once valid. Groundworks and the base often take a few weeks, depending on the site and curing time. Installing the frame, glass, turf and lights is usually much quicker once the base is ready.

How a Padel Court Is Built: Stages and Timeline

Stage 1: feasibility and design

Every project starts with checking the site works. That means confirming there is space for the 20 by 10 metre court plus surrounds, assessing slope, ground conditions, access for machinery and glass deliveries, buried services and the position of neighbours. A topographical survey and, on uncertain ground, a ground investigation help the contractor design the base properly.

At this stage you choose the court type, decide on lighting and any canopy, and agree orientation. Early decisions on ducting for power, lighting and booking systems save money later.

For clubs and commercial venues, feasibility also covers the business side: likely demand, booking prices, opening hours and whether lighting or a canopy will be needed to make the numbers work through the winter months.

  • Site measurement and topographical survey
  • Ground conditions and drainage assessment
  • Access for machinery and glass deliveries
  • Court type, lighting and canopy decisions
  • Orientation, noise and neighbour considerations

Stage 2: planning permission

Most padel courts need planning permission because of the enclosure height and, often, floodlighting. The application usually includes site plans, court elevations, a lighting plan and, where required, a noise assessment. Using pre-application advice from the council can identify issues before a full application. Many councils aim to decide minor applications within eight weeks of a valid application, though more complex schemes can take longer.

Ordering a court before planning is granted carries risk. Many buyers secure planning first, then confirm the order and installation dates.

Stage 3: groundworks and base

Groundworks start with stripping topsoil and excavating to formation level. On sloping sites, the ground is cut and filled to create a level platform. A compacted stone sub-base follows, with drainage installed around the perimeter and, where needed, beneath the base. Ducts for power to floodlights, booking systems and access control are laid before the base is formed.

The base itself is either a reinforced concrete slab or porous asphalt, built to the court maker's tight flatness tolerances. Concrete needs time to cure before the frame is fixed to it, which is a key factor in the overall timeline.

StageWhat happensTypical duration
Feasibility and designSurvey, layout, court and lighting choicesA few weeks
PlanningApplication, consultation, decisionOften around 8 weeks once valid
Groundworks and baseExcavation, sub-base, drainage, slab or asphaltOften a few weeks including curing
Court installationFrame, glass, mesh, doorsUsually days rather than weeks
Turf and lightingTurf, markings, sand infill, LED lightsA few days
HandoverChecks, maintenance guidanceFinal day

Stage 4: court installation

Once the base is ready, the installation crew sets out the frame and fixes the steel posts and base plates to the slab. Glass panels are lifted into position, often with specialist lifting equipment, and secured with the manufacturer's fixings. Welded mesh panels and doors follow. Panoramic courts use their own glass fixing systems and need crews familiar with them.

The glass is toughened safety glass, commonly manufactured to BS EN 12150. Careful handling and correct fixing are essential, because damaged edges can weaken a panel.

Once the frame and glass are up, the crew checks that all doors open and close freely and that panels sit evenly.

Stage 5: turf, markings and lighting

The artificial turf is rolled out across the base, joined and glued, and the court lines are inlaid or marked. Sand infill is spread and brushed into the turf to give consistent bounce and grip. Floodlights are mounted on the frame, cabled through the ducts laid earlier and commissioned. The electrical installation should comply with BS 7671, and lighting is aimed to keep light on the court and limit spill, in line with any planning conditions.

Where a canopy is included, its foundations are usually formed during groundworks, with the structure erected before or after the court depending on the design.

Stage 6: handover and maintenance

At handover, the contractor should walk the court with you, check doors, glass, net and lighting, and explain the maintenance routine. Turf brushing, sand top-ups, glass cleaning and leaf clearing keep the court playing well. Keep records of the court specification, glass certificates, electrical certification and any planning conditions, such as permitted hours of use.

We arrange padel court construction through vetted, insured specialist contractors, from groundworks to final installation. Describe your site and plans in the quote form and you will receive one all-in price.

What can delay a project

Weather is the most common cause of delay. Groundworks slow down in prolonged rain, concrete pours are avoided in hard frost and turf is best laid in dry conditions. Planning delays can push the whole programme back, as can unexpected ground conditions such as soft spots, buried obstructions or a high water table. Lead times for court kits and glass also vary through the year, so confirming orders early helps keep the programme on track.

Access problems can also cause delays. Glass panels and steel sections arrive on large vehicles, and a narrow lane, low bridge or soft verge may mean transferring loads to smaller vehicles. Checking the route in advance, and agreeing where deliveries will be unloaded and stored, keeps installation days on schedule.

Questions people also ask

How long does it take to build a padel court?

Once planning is in place, groundworks and the base often take a few weeks, including time for concrete to cure, and installing the frame, glass, turf and lighting is usually a matter of days. Planning, design and lead times for the court kit add to the overall timeline.

What base does a padel court need?

A padel court needs a level, well-drained base, usually a reinforced concrete slab or porous asphalt on a compacted stone sub-base. It must meet the court manufacturer's tight flatness tolerances, with perimeter drainage and ducts for lighting and power laid before the base is formed.

Can a padel court be built in winter?

Court installation can go ahead in most winter weather, but groundworks slow in heavy rain, concrete pours are avoided during hard frost and turf is best laid when dry. Many projects plan groundworks for drier months, or allow extra time in the programme for weather.

Written and checked by the Padel Court Construction team. Read our editorial policy.